Weekly Data Statistics on Maintenance of Propylene Oxide Plants in China

Published on 2026-10-16

Table: Domestic Propylene Oxide Plant Maintenance Schedule (October 16, 2026)

Region Enterprise Name Capacity (10k tons/year) Unit Status
Northeast Hangjin Technology 12 The 40k ton small unit experienced a fault on Sep. 10 and is undergoing maintenance at half load, possibly lasting until year-end; the large unit is operating normally at full capacity.
North China Tianjin Bohua 20 Operating at 90% load.
Tianjin Petrochemical 15 Operating normally at full capacity.
Shandong Shandong Binhua 28 Operating normally at full capacity. Dongrui's 80k ton unit is tentatively scheduled for shutdown maintenance in November, with downstream polyether units synchronously shutting down for an estimated 14 days.
Shandong Xinyue 30 Operating at 90% load. Downstream polyether units will undergo phased shutdowns for upgrades from Oct. 15 to Nov. 25.
Shida Shenghua 7 Operating normally at full capacity.
Wanhua Chemical 154 Phases 1-4 are operating at slightly reduced load. Phase 3 output may be reduced by month-end, specifics TBD.
Shandong Jinling 16 Operating normally at full capacity. Rotating shutdown maintenance for 7-10 days is tentatively scheduled for Oct. 20.
Shandong Sanyue 32 Shut down for maintenance on Oct. 14. One line may restart later, specifics TBD.
Dongying Huatai 8 Operating at half load since Oct. 15, expected to last 6 days.
Zhonghai Fine Chemical 8 Shut down.
Qixiang Tengda 30 Load slightly reduced to approximately 60%.
Jincheng Petrochemical 30 Shut down.
Lihua Yiweiyuan 30 Operating normally at full capacity.
Binhua New Materials 24 Operating normally at full capacity.
Minxiang Chemical 15 Shut down on Feb. 13, 2026. Restart time TBD.
Dongming Guoen 8 Shut down on Dec. 21, 2025. Indicated possible restart in the near future.
Lianhong Gerun 30 Operating at 70-80% load.
East China Jinling Huntsman 24 Operating at approximately 80% load.
Ningbo Hai'an 57 Phase 1 operating at 90% load. Phase 2 shut down for maintenance on Sep. 24, 2025.
Zhenhai Refining & Chemical 30 Operating at 90% load.
Hongbaoli 16 Shut down.
Jiangsu Fuqiang 10 Shut down.
Taixing Yida 15 Shut down.
Jiahong New Materials 40 Operating at approximately 70-80% load.
Zhejiang Petrochemical 27 Operating at 70-80% load. Annual maintenance tentatively scheduled for early November.
Ruiheng New Materials 40 Load slightly reduced to approximately 50-60%.
Shenghong Petrochemical 20 Shut down for maintenance on May 28. Restart time TBD.
South China Sinopec Quanzhou 20 Operating at 90% load.
Guangxi Petrochemical 27 Operating at 60% load.
Central China Sinopec Changling 10 Operating normally at full capacity.

Data Source: Chempricehub News