Table 2026 Domestic Propylene Oxide Plant Maintenance Schedule (November 13, 2026)
| Region | Company Name | Capacity (10k t/a) | Unit Status |
|---|---|---|---|
| Northeast | Hangjin Technology | 12 | The 40k t/a unit experienced a fault on September 10 and is undergoing maintenance at half load, potentially continuing until year-end; the large unit is reducing to half load this week due to column cleaning. |
| North China | Tianjin Bohua | 20 | Operating at 90% load. |
| Tianjin Petrochemical | 15 | Operating at 80% load. | |
| Shandong | Binzhou Chemical | 28 | The 200k t/a unit is operating normally at full capacity. The Dongrui 80k t/a unit shut down for maintenance on November 3, with downstream polyether units synchronized; estimated duration: 14 days. |
| Shandong Xinyue | 30 | Operating near full capacity. Downstream polyether units will undergo sequential shutdowns for upgrades from October 15 to November 25. | |
| Shida Shenghua | 7 | Operating normally at full capacity. | |
| Wanhua Chemical | 154 | Units 1, 2, and 4 are operating at slightly reduced loads. Unit 3 shut down for maintenance on October 27, expected to last until late in the month (specific date TBD). | |
| Shandong Jinling | 16 | Operating normally at full capacity. | |
| Shandong Sanyue | 32 | One production line shut down on October 29 for column cleaning; expected to resume next week. | |
| Dongying Huatai | 8 | Briefly operated at half load earlier in the week but has returned to normal full-capacity operation. | |
| Zhonghai Fine Chemicals | 8 | Shut down. | |
| Qixiang Tengda | 30 | Operating at approximately 50% load. | |
| Jincheng Petrochemical | 30 | Shut down. | |
| Liuhua Yiwei Yuan | 30 | Operating at slightly reduced load earlier in the week. | |
| Binhua New Materials | 24 | Load gradually reduced starting November 10 to approximately 60–70%. | |
| Minxiang Chemical | 15 | Shut down on February 13, 2026; restart time TBD. | |
| Dongming Guoen | 8 | Shut down on December 21, 2025. Factory reports restart began this week; product output may begin next week. | |
| Lianhong Gerun | 30 | Operating at 70–80% load. | |
| East China | Jinling Huntsman | 24 | Operating normally at full capacity. |
| Ningbo Hai'an | 57 | Phase I operating at 90% load. Phase II shut down for maintenance on September 24, 2025. | |
| Zhenhai Refining & Chemical | 30 | Operating at 90% load. | |
| Hongbaoli | 16 | Shut down. | |
| Jiangsu Fuqiang | 10 | Shut down. | |
| Taixing Yida | 15 | Restarted earlier in the week; operating at slightly reduced load. | |
| Jiahong New Materials | 40 | Operating at approximately 70–80% load. | |
| Zhejiang Petrochemical | 27 | Operating at 70–80% load. Annual maintenance scheduled to start November 16 for 50 days (tentative). | |
| Ruiheng New Materials | 40 | Operating at approximately 50% load. | |
| Shenghong Petrochemical | 20 | Shut down for maintenance on May 28; restart time TBD. | |
| South China | Sinochem Quanzhou | 20 | Operating at 90% load. |
| Guangxi Petrochemical | 27 | Operating at 60% load. | |
| Central China | Sinopec Changling | 10 | Operating normally at full capacity. |
Data Source: Chempricehub Information