Overview of Domestic Acrylonitrile Plant Operations

Published on 2026-10-16
Enterprise Name Capacity Current Operating Rate Unit Status
Fushun Petrochemical 9.2 0% Shut down in early March; restart planned for mid-September.
Jilin Petrochemical 68.4 85% Load reduced to 50% from mid-April to mid-May; one 130 kt/a line shut down for maintenance on June 1, resumed in July; PP Line 1 and PP Line 3A shut down for maintenance at the end of July; PP Line 3A resumed on August 18.
Daqing Petrochemical 8 90% Shutdown for maintenance from September 7 to 21.
Daqing Refining & Chemical 8 100% None.
Anqing Petrochemical 21 0% Load reduced in late January, increased in mid-March; the 80 kt/a unit shut down on September 2, and the 130 kt/a unit shut down on September 8, with an expected duration of 40–50 days.
Shandong Haijiang 13 100% Shutdown for maintenance from December 25, 2025, to February 8, 2026; short outage due to fault from August 19 to 21; shutdown for maintenance from September 17 to 28.
Kerur 26 90% Shutdown for maintenance starting April 23; gradual restart beginning June 23.
Shanghai Secco 52 50% Only one unit has been operating since March 2025; one line underwent maintenance from May 6 to 21, reducing load to 25%.
Sierbang 104 50% Operation reduced from three units to two starting January 20; restored to three units by late March; reduced to two units in June; reduced to one unit in July; gradually restored to three units in early September; PP Line 1 shut down again on September 23.
Lanzhou Petrochemical 3.5 90% None.
Zhejiang Petrochemical 52 60% Load reduced for maintenance in late January, gradually increased in February; one unit shut down at the end of March, one line resumed in mid-May, and the other line resumed on June 20; one line shut down for maintenance due to a fault from August 14 to 27; one line shut down again in early September and resumed on September 29; another line shut down from October 10 to 19.
Liuhua Yi 26 100% Short outage for repair due to a fault on July 28; restarted on August 5.
Tianchen Qixiang 13 100% Load reduced in mid-March; shutdown for maintenance in early July, resumed on August 20.
Liaoning Kingfa 26 100% One 130 kt/a production line underwent maintenance on August 13, resumed in early September.
Jihua (Jieyang) 13 90% Shutdown for maintenance due to a fault starting January 20, restarted on February 10; short outage due to a fault from July 29 to August 3; maintenance planned for December.
CNOOC Fudao 20 95% Shutdown for maintenance on March 30; one line resumed at the end of April, and the other line resumed in early May.
Yulong Petrochemical 26 95% Line 2 successfully started up in early February.
Sinochem Quanzhou 26 90% Full-line shutdown for maintenance in mid-September 2025; gradual restart around June 25.
Zhenhai Refining & Chemical 40 80% Load reduced in late January; dropped to 80% in July; further reduced to 50% starting August 10, with gradual recovery in early September.
Sinopec (Tianjin) 13 90% Scheduled to commence operations in mid-September 2026.
Total 568.1 72.1%