China producers · plant capacity (10kt) · capacity utilization
Latest China snapshot 20261116
Track PTA plant capacity and capacity utilization by producer. Operating rates, shutdowns and restarts that move China supply. Compare with PTA price or browse PTA suppliers.
| Producer | Plant capacity (10kt) | Utilization % | Remark |
|---|---|---|---|
| BP Zhuhai Chemical Co., Ltd. | 235.00 | - | The 1.1 million tons/year unit will undergo a shutdown on April 19, 2026, with the restart date to be determined (TBD). The 1.25 million tons/year unit was shut down in mid-January 2026 and restarted on February 28; it experienced a short shutdown for repairs on September 24, followed by another unplanned shutdown on November 11 due to operational issues. |
| Chongqing Pengwei Petrochemical Co., Ltd. | Shutdown on August 29, 2024 | ||
| Dongying Weilian Chemical Co., Ltd. | The unit was shut down on June 29, 2026, for load reduction. It was restarted on August 27, 2026, and is currently undergoing ramp-up to nominal capacity. | ||
| Formosa Chemicals Industries (Ningbo) Co., Ltd. | The 1.2 million tons/year unit restarted on May 9, 2026, and is currently shut down as of June 30. The 1.5 million tons/year unit was shut down on May 10, 2026, and restarted on June 12. On August 6, it reduced its load to 85% due to operational issues; the load was restored starting August 13, followed by a one-day temporary shutdown on August 14. | ||
| Fujian Billion Petrochemicals Co., Ltd. | The plant will be shut down on November 1, 2026, and reheated for restart on November 14. | ||
| Fujian Fuhai Chuang Petrochemical Co., Ltd. | Shutdown on June 25, 2026; restart in early September. Power trip occurred on September 8, followed by restoration. In early November, product quality and output were briefly affected. | ||
| Hainan Yisheng Petrochemical Co., Ltd. | The 2.0 million ton/year unit was shut down on August 16, 2025, and restarted on June 1, 2026; it was subsequently shut down again on July 10. The 2.5 million ton/year unit was shut down on June 4, 2026, and restarted on July 5. Recently, the plant has undergone a slight reduction in operating load. | ||
| Hanbang (Jiangyin) Petrochemical Co., Ltd. | Shutdown on January 6, 2025 | ||
| Hengli Petrochemical (Huizhou) Co., Ltd. | The 2.5 million tons/year unit will undergo a two-week shutdown starting May 10, 2026, followed by a short outage of 4–5 days beginning May 29, 2026. The other 2.5 million tons/year unit will reduce load on September 20, 2025, and experience a brief outage lasting several days around August 5, after which it will resume operations. | ||
| Hengli Petrochemical Co., Ltd. | The 2.2 million tons/year unit was shut down on October 9, 2025, and restarted on October 24, 2025. Another 2.2 million tons/year unit was shut down in mid-June 2025 and restored by the end of June; it also underwent load reduction and shutdown starting September 2, followed by restoration. The third 2.2 million tons/year unit is scheduled to be shut down on April 20, 2026. One 2.5 million tons/year unit will be shut down on April 9, 2026, with a restart planned for late April. Another 2.5 million tons/year unit will be shut down on April 25, 2026, with a restart expected in early-to-mid June. | ||
| Jiangsu Hailun Petrochemical Co., Ltd. | The 1.2 million ton/year unit will be shut down on August 28, 2025. The other 1.2 million ton/year unit was shut down on July 2, 2023, restarted on September 28, and shut down again on October 7. The 3.2 million ton/year unit is scheduled to be shut down on April 22, 2026, with a restart and gradual load increase planned for September 20; subsequent load reductions are expected to commence in November. | ||
| Jiangsu Honggang Petrochemical Co., Ltd. | The 2.5 million ton/year unit will be restarted on June 1, 2026, following a shutdown on May 23, 2026. It will undergo another planned outage on July 3, 2026, with restart and load ramp-up scheduled for September 1, 2026. A planned load reduction is anticipated from late October to November 2026, with an early recovery expected thereafter. The second 2.5 million ton/year unit is scheduled for shutdown on July 1, 2026, with product discharge completed by August 26, 2026, after which the unit will enter its load ramp-up phase. | ||
| Jiangsu Jiatong Energy Co., Ltd. | The 3 million tons/year unit reduced its load to 70–80% on August 6, 2026, due to operational issues, and restored full capacity on August 14. It was scheduled for a two-week shutdown starting in mid-October 2026. Another 3 million tons/year unit was shut down on May 20, 2026, and restarted on June 3. On August 6, 2026, it also reduced its load to 70–80% due to operational issues, with capacity fully restored on August 14. | ||
| Jiaxing Petrochemical Co., Ltd. | The 1.5 million tons/year unit experienced a 5-day unplanned shutdown starting March 13, 2026; it was shut down on July 1 and restarted on September 3; another shutdown occurred around October 6. The 2.2 million tons/year unit was shut down on May 5, 2026, and is currently in the process of restarting as of May 15, 2026. | ||
| Ningbo Yisheng Petrochemical Co., Ltd. | The 2.0 million tons/year unit will shut down on January 25, 2025; the 2.2 million tons/year unit will shut down on November 20, 2025, and restart on December 24, 2025. | ||
| Sichuan Provincial Energy Investment Group Co., Ltd. | Shutdown scheduled for April 15, 2026 has been postponed. | ||
| Sinopec Yizheng Chemical Fibre Co., Ltd. | The 650,000-ton-per-year unit was shut down on April 10, 2024. The 3-million-ton-per-year unit was shut down on March 3, 2026, and restarted on March 20, 2026. Its operating rate dropped to 70–80% in late July to early August before recovering to near-full capacity. | ||
| Xinjiang Zhongtai Chemical Co., Ltd. | Shutdown on July 1, 2026; restart on July 25. Load increased to approximately 90% in early August, then decreased to 80% in early September. The plant was shut down again on September 14 due to an operational issue. Restarted on September 23, with product output ramping up and load increasing. | ||
| Yisheng Dahua Petrochemical Co., Ltd. | Here is the professional English translation of the operational timeline: **2.25 Million Tons/Year (MTPA) Unit:** * Shut down on August 8, 2025. * Restarted in July 2026. * Unplanned shutdown occurred on August 26, 2026; restarted on September 13, 2026. **3.75 MTPA Unit:** * Load reduced on October 31, 2025; load increased back to normal on November 6, 2025. * Underwent technical modification starting August 1, 2026. * Currently restarting as of mid-November 2026. | ||
| Zhejiang Dushan Energy Co., Ltd. | The 2.5 million tons/year unit will undergo a shutdown on May 16, 2026, and restart on June 15, 2026. From August 4 to 14, it will reduce its operating rate to 70% due to operational issues. A short shutdown for repairs is scheduled for September 22, 2026, followed by a minor load reduction in November. Another 2.5 million tons/year unit will shut down on February 10, 2026, and restart on February 28, 2026. It will experience an unplanned shutdown from August 1 to August 23, 2026, due to operational issues, followed by a minor load reduction in November. The 3.0 million tons/year unit will begin reducing its load on June 12, 2026, proceed to a full shutdown on June 24, 2026, and commence restart procedures on July 24, 2026. From August 4 to 14, 2026, it will operate at 70% capacity due to operational issues, followed by a minor load reduction in November. Another 3.0 million tons/year unit will shut down on April 14, 2026, and restart on May 9, 2026. It will operate at 70% capacity from August 4 to 14, 2026, due to operational issues, and will undergo a planned shutdown from October 3 to 28, 2026. | ||
| Zhejiang Yisheng New Materials Co., Ltd. | The 3.6 million ton/year unit experienced an unplanned shutdown on February 24, 2026, due to unforeseen circumstances. It resumed operation and increased load on February 25, with full recovery achieved in early March. Load reduction began on March 12, followed by a 30% load cut on April 2. As of August 14, the unit is undergoing load ramp-up. Another 3.6 million ton/year unit was shut down on January 14, 2026, and restarted with increasing load on February 25. It underwent a 30% load reduction on April 2 and is currently in the process of load ramp-up as of August 14. |
| Producer | Plant capacity (10kt) | Utilization % | Remark |
|---|---|---|---|
| BP Zhuhai Chemical Co., Ltd. | Shutdown scheduled for April 19, 2026; restart date to be determined. | ||
| Chongqing Pengwei Petrochemical Co., Ltd. | Shutdown on August 29, 2024; | ||
| Dongying Weilian Chemical Co., Ltd. | Unit shut down for load reduction on June 29, 2026; restarted and currently ramping up on August 27. | ||
| Formosa Chemicals Industries (Ningbo) Co., Ltd. | Restart on May 9, 2026; Shutdown in progress as of June 30. | ||
| Fujian Billion Petrochemicals Co., Ltd. | Shutdown on November 1, 2026; restart with ramp-up in temperature over the past two days. | ||
| Fujian Fuhai Chuang Petrochemical Co., Ltd. | Shutdown on June 25, 2026; restart in early September. Power trip occurred on September 8 and was subsequently restored. Early November saw a brief impact on product quality and production volume. | ||
| Hainan Yisheng Petrochemical Co., Ltd. | Shutdown on August 16, 2025; restart on June 1, 2026; shutdown again on July 10. | ||
| Hanbang (Jiangyin) Petrochemical Co., Ltd. | Shutdown on January 6, 2025 | ||
| Hengli Petrochemical (Huizhou) Co., Ltd. | Shutdown scheduled for May 10, 2026, lasting approximately two weeks; short shutdown planned from May 29 to early June (4–5 days). | ||
| Hengli Petrochemical Co., Ltd. | The plant was shut down on October 9, 2025, and restarted on October 24, 2025. | ||
| Jiangsu Hailun Petrochemical Co., Ltd. | Shutdown on August 28, 2025 | ||
| Jiangsu Honggang Petrochemical Co., Ltd. | On May 23, 2026, the unit was shut down; it restarted on June 1. On July 3, it was shut down again, and restarted on September 1 with a gradual load ramp-up. From late October to November, the unit operated at reduced load, with an early restoration of full capacity. | ||
| Jiangsu Jiatong Energy Co., Ltd. | On August 6, 2026, the plant load was reduced to 70–80% due to unforeseen circumstances; the load was increased on August 14; and from mid-October, the unit was shut down for approximately two weeks. | ||
| Jiaxing Petrochemical Co., Ltd. | On March 13, 2026, a short shutdown of five days was implemented due to unforeseen circumstances. The plant was shut down on July 1 and restarted on September 3. Another shutdown occurred around October 6. | ||
| Ningbo Yisheng Petrochemical Co., Ltd. | Shutdown on January 25, 2025 | ||
| Sichuan Provincial Energy Investment Group Co., Ltd. | Shutdown scheduled for April 15, 2026: Postponed | ||
| Sinopec Yizheng Chemical Fibre Co., Ltd. | Shutdown on April 10, 2024; | ||
| Xinjiang Zhongtai Chemical Co., Ltd. | Shutdown on July 1, 2026; restart on July 25. Load increased to approximately 90% in early August; decreased to 80% in early September. Shutdown due to operational issues on September 14; restarted on September 23, with product output and load currently ramping up. | ||
| Yisheng Dahua Petrochemical Co., Ltd. | Shutdown on August 8, 2025; restart in progress on July 15, 2026; unplanned shutdown on August 26 due to operational issues; restart on September 13. | ||
| Zhejiang Dushan Energy Co., Ltd. | Shutdown on May 16, 2026; restart on June 15. Reduced to 70% capacity from August 4–14 due to unforeseen circumstances. Short shutdown on September 22 for repairs following an incident. Minor load reduction in November. | ||
| Zhejiang Yisheng New Materials Co., Ltd. | The unit was temporarily shut down on February 24, 2026, due to unforeseen circumstances. It resumed ramping up on February 25, with full capacity restored in early March. Load reduction commenced on March 12. On April 2, the load was reduced by 30%. As of August 14, the unit is undergoing a gradual increase in load. |
| Producer | Plant capacity (10kt) | Utilization % | Remark |
|---|---|---|---|
| BP Zhuhai Chemical Co., Ltd. | Shutdown scheduled for April 19, 2026; restart date TBD. | ||
| Chongqing Pengwei Petrochemical Co., Ltd. | Shutdown on August 29, 2024 | ||
| Dongying Weilian Chemical Co., Ltd. | On June 29, 2026, the unit was shut down following a load reduction. On August 27, it was restarted and is currently undergoing a gradual increase in load (ramp-up). | ||
| Formosa Chemicals Industries (Ningbo) Co., Ltd. | Recommissioning on May 9, 2026; currently in shutdown status as of June 30. | ||
| Fujian Billion Petrochemicals Co., Ltd. | Shutdown on November 1, 2026; restart with gradual temperature ramp-up over the past two days. | ||
| Fujian Fuhai Chuang Petrochemical Co., Ltd. | The plant was shut down on June 25, 2026, and restarted in early September. Power restoration followed a trip event on September 8. In early November, there was a brief impact on product output and production volume. | ||
| Hainan Yisheng Petrochemical Co., Ltd. | Shutdown on August 16, 2025; restart on June 1, 2026; shutdown again on July 10. | ||
| Hanbang (Jiangyin) Petrochemical Co., Ltd. | Shutdown on January 6, 2025 | ||
| Hengli Petrochemical (Huizhou) Co., Ltd. | Shutdown scheduled for May 10, 2026, lasting approximately two weeks; followed by a short shutdown of 4–5 days on May 29. | ||
| Hengli Petrochemical Co., Ltd. | Shutdown on October 9, 2025; restart on October 24, 2025 | ||
| Jiangsu Hailun Petrochemical Co., Ltd. | Shutdown on August 28, 2025 | ||
| Jiangsu Honggang Petrochemical Co., Ltd. | Shutdown on May 23, 2026; Restart on June 1. Shutdown on July 3; Restart and capacity ramp-up in progress as of September 1. Load reduction scheduled for late October to November, with early restoration planned. | ||
| Jiangsu Jiatong Energy Co., Ltd. | On August 6, 2026, the plant load was reduced to 70–80% due to operational issues. The load was restored on August 14. Starting in mid-October, the unit underwent a shutdown for approximately two weeks. | ||
| Jiaxing Petrochemical Co., Ltd. | Short shutdown of 5 days on March 13, 2026, due to unforeseen circumstances; plant shut down on July 1 and restarted on September 3; another shutdown occurred around October 6. | ||
| Ningbo Yisheng Petrochemical Co., Ltd. | Shutdown on January 25, 2025 | ||
| Sichuan Provincial Energy Investment Group Co., Ltd. | Shutdown postponed to April 15, 2026 | ||
| Sinopec Yizheng Chemical Fibre Co., Ltd. | Shutdown on April 10, 2024 | ||
| Xinjiang Zhongtai Chemical Co., Ltd. | Shutdown on July 1, 2026; restart on July 25. Load increased to approximately 90% in early August; reduced to 80% in early September. Shutdown due to operational issues on September 14; restarted on September 23, with product output and load ramping up. | ||
| Yisheng Dahua Petrochemical Co., Ltd. | Shutdown on August 8, 2025; restart in progress as of July 15, 2026; unplanned shutdown on August 26 due to operational issues; restart on September 13. | ||
| Zhejiang Dushan Energy Co., Ltd. | Shutdown on May 16, 2026; restart on June 15. From August 4 to 14, the plant operated at 70% load due to operational issues. A short shutdown occurred on September 22 due to a fault, followed by repairs. Minor load reduction was implemented in November. | ||
| Zhejiang Yisheng New Materials Co., Ltd. | The plant was temporarily shut down on February 24, 2026, due to unforeseen circumstances. Load recovery commenced on February 25, with full capacity restored by early March. The load was reduced starting March 12; a further 30% reduction in load occurred on April 2. As of August 14, the unit is in the process of ramping up its load. |
| Producer | Plant capacity (10kt) | Utilization % | Remark |
|---|---|---|---|
| BP Zhuhai Chemical Co., Ltd. | Unit 1: Shutdown on April 19, 2026; restart date to be determined (TBD). Unit 2: Shutdown in January 2026, restarted on February 28; following a short shutdown on September 24, repairs were completed. | ||
| Chongqing Pengwei Petrochemical Co., Ltd. | Shutdown on August 29, 2024 | ||
| Dongying Weilian Chemical Co., Ltd. | On June 29, 2026, the unit was shut down following a load reduction. As of August 27, it has been restarted and is currently undergoing load ramp-up. | ||
| Formosa Chemicals Industries (Ningbo) Co., Ltd. | Unit 1: Restarted on May 9, 2026; currently in shutdown status as of June 30. Unit 2: Shut down on May 10, 2026; restarted on June 12. On August 6, the load was reduced to 85% due to operational issues. The load was restored on August 13, followed by a one-day temporary shutdown on August 14. | ||
| Fujian Billion Petrochemicals Co., Ltd. | Shutdown on November 1, 2026 | ||
| Fujian Fuhai Chuang Petrochemical Co., Ltd. | The unit was shut down on June 25, 2026, and restarted in early September. It recovered following a power trip on September 8. In early November, there was a brief impact on product output and production volume. | ||
| Hainan Yisheng Petrochemical Co., Ltd. | Unit 1: Shut down on August 16, 2025; restarted on June 1, 2026; shut down again on July 10. Unit 2: Shut down on June 4, 2026; restarted on July 5. Recently, the unit has been operating at a slightly reduced load. | ||
| Hanbang (Jiangyin) Petrochemical Co., Ltd. | Shutdown on January 6, 2025 | ||
| Hengli Petrochemical (Huizhou) Co., Ltd. | Unit 1: Shutdown on May 10, 2026, for approximately two weeks; short shutdown from May 29 to June 2/3 (4–5 days). Unit 2: Load reduction on September 20, 2025; short shutdown in early August (a few days) followed by restart. | ||
| Hengli Petrochemical Co., Ltd. | The scope includes multiple units (2.2/2.2/2.2/2.5/2.5 million tons/year), involving numerous shutdowns, restarts, and technical upgrades during 2025–2026. | ||
| Jiangsu Hailun Petrochemical Co., Ltd. | Unit 1: Shut down on August 28, 2025. Unit 2: Shut down on July 2, 2023; restarted on September 28, 2023; shut down again on October 7, 2023. Unit 3: Shut down on April 22, 2026; restarted on September 20, 2026, and currently undergoing load ramp-up. | ||
| Jiangsu Honggang Petrochemical Co., Ltd. | Unit 1: Shut down on May 23, 2026; restarted on June 1. Shut down again on July 3; currently undergoing load ramp-up following the September 1 restart. Planned to reduce load in late October–November, with an early recovery scheduled. Unit 2: Shut down on July 1, 2026; product discharge completed on August 26; currently undergoing load ramp-up. | ||
| Jiangsu Jiatong Energy Co., Ltd. | Unit 1: Reduced load to 70–80% on August 6, 2026, due to operational issues; restored to normal load on August 14, 2026; shut down for approximately two weeks starting mid-October 2026. Unit 2: Shut down on May 20, 2026, and restarted on June 3, 2026; reduced load to 70–80% on August 6, 2026, due to operational issues; restored to normal load on August 14, 2026. | ||
| Jiaxing Petrochemical Co., Ltd. | Unit 1: A five-day unplanned shutdown occurred on March 13, 2026; the unit was shut down on July 1 and restarted on September 3; another shutdown took place around October 6. Unit 2: The unit was shut down on May 5, 2026, with a restart scheduled for May 15. | ||
| Ningbo Yisheng Petrochemical Co., Ltd. | Shutdown on January 25, 2025; Shutdown on November 20, 2025, and restart on December 24, 2025. | ||
| Sichuan Provincial Energy Investment Group Co., Ltd. | Shutdown scheduled for April 15, 2026, postponed. | ||
| Sinopec Yizheng Chemical Fibre Co., Ltd. | Unit 1: Shut down on April 10, 2024. Unit 2: Shut down on March 3, 2026; restarted on March 20. In late July to early August, the load was reduced to 70–80% of capacity and has since largely recovered. | ||
| Xinjiang Zhongtai Chemical Co., Ltd. | Shutdown on July 1, 2026; restarted on July 25. In early August, the load was ramped up to approximately 90%. By early September, it had been reduced to 80%. A shutdown occurred on September 14 due to operational issues. The unit was restarted on September 23 and is currently in the process of discharging product while increasing the load. | ||
| Yisheng Dahua Petrochemical Co., Ltd. | Unit 1: Shutdown on August 8, 2025; restart in progress as of July 15, 2026; shutdown due to unforeseen circumstances on August 26, 2026; restarted on September 13, 2026. Unit 2: Load reduction on October 31, 2025; load increase on November 6, 2025; technical modification implemented on August 1, 2026. | ||
| Zhejiang Dushan Energy Co., Ltd. | The project comprises four units (250/250/300/300 million tons/year), involving multiple shutdowns, restarts, load reductions to 70% capacity, and minor load adjustments throughout 2026. | ||
| Zhejiang Yisheng New Materials Co., Ltd. | Unit 1: Unscheduled shutdown on February 24, 2026; load ramp-up resumed on February 25, with full capacity restored in early March. Load reduction began on March 12; output reduced by 30% on April 2; currently ramping up as of August 14. Unit 2: Shut down on January 14, 2026; restarted and ramping up on February 25. Output reduced by 30% on April 2; currently ramping up as of August 14. |
| Producer | Plant capacity (10kt) | Utilization % | Remark |
|---|---|---|---|
| BP Zhuhai Chemical Co., Ltd. | 1.1 million ton/year unit: Shutdown on April 19, 2026; restart date to be determined (TBD). 1.25 million ton/year unit: Shutdown in January 2026; restarted on February 28, 2026; following a brief shutdown on September 24, repairs were completed and the unit was restored to operation. | ||
| Chongqing Pengwei Petrochemical Co., Ltd. | 900,000-ton-per-year unit: Shutdown on August 29, 2024 | ||
| Dongying Weilian Chemical Co., Ltd. | 2.5-million-ton-per-year unit: Load reduction and shutdown on June 29, 2026; restarted with increasing load on August 27. | ||
| Formosa Chemicals Industries (Ningbo) Co., Ltd. | 1.2 million ton/year unit: Restarted on May 9, 2026; currently shut down as of June 30, 2026. 1.5 million ton/year unit: Shut down on May 10, 2026; restarted on June 12, 2026. On August 6, the load was reduced to 85% due to an incident; recovery in progress on August 13; temporary shutdown for one day on August 14. | ||
| Fujian Billion Petrochemicals Co., Ltd. | 2.5 million ton per year unit: Shutdown on November 1, 2026 | ||
| Fujian Fuhai Chuang Petrochemical Co., Ltd. | For the 4.5 million tons per annum (MTPA) unit: Shutdown commenced on June 25, 2026, with restart scheduled for early September; power interruption occurred on September 8 but was subsequently restored; minor impacts on product output and production volume were observed in early November. | ||
| Hainan Yisheng Petrochemical Co., Ltd. | 2-million-tonne-per-annum (MTPA) unit: Shut down on August 16, 2025; restarted on June 1, 2026; shut down again on July 10. 2.5-MTPA unit: Shut down on June 4, 2026; restarted on July 5. Recently operating at a slightly reduced load. | ||
| Hanbang (Jiangyin) Petrochemical Co., Ltd. | Shutdown of the 2.2 million ton/year unit on January 6, 2025 | ||
| Hengli Petrochemical (Huizhou) Co., Ltd. | Unit 1 (2.5 million tons/year): Scheduled shutdown on May 10, 2026, lasting approximately two weeks; a short turnaround of 4–5 days on May 29. Unit 2 (2.5 million tons/year): Load reduction starting September 20, 2025; a brief shutdown in early August for several days, followed by resumption of operations. | ||
| Hengli Petrochemical Co., Ltd. | Here is the professional translation of the provided text: **Shutdown and Restart Schedule for Cracking Units:** * **2.2 Million TPA Unit 1:** Shutdown on October 9, 2025; restart on October 24, 2025. * **2.2 Million TPA Unit 2:** Shutdown in mid-June 2025; restored to operation by late June 2025. Additionally, following a load reduction and shutdown initiated on September 2, 2025, the unit was subsequently restarted. * **2.2 Million TPA Unit 3:** Scheduled for shutdown on April 20, 2026. * **2.5 Million TPA Unit 1:** Scheduled for shutdown on April 9, 2026; restart expected later in the same month. * **2.5 Million TPA Unit 2:** Scheduled for shutdown on April 25, 2026; restart expected in early-to-mid June 2026. | ||
| Jiangsu Hailun Petrochemical Co., Ltd. | Here is the professional English translation for the chemical engineering context: **Unit 1 (1.2 MTPA):** Shutdown on August 28, 2025. **Unit 2 (1.2 MTPA):** Shutdown on July 2, 2023; restarted on September 28, 2023; shutdown again on October 7, 2023. **Unit 3 (3.2 MTPA):** Shutdown on April 22, 2026; restarted on September 20, 2026, currently undergoing load-up/ramp-up. | ||
| Jiangsu Honggang Petrochemical Co., Ltd. | Unit 1 (2.5 million tons/year capacity): - Shutdown on May 23, 2026; restarted on June 1, 2026. - Shutdown again on July 3, 2026; restarted on September 1, 2026, with load ramp-up in progress. - Planned load reduction from late October to November 2026, with early recovery anticipated. Unit 2 (2.5 million tons/year capacity): - Shutdown on July 1, 2026; product discharge completed on August 26, 2026, with load ramp-up currently underway. | ||
| Jiangsu Jiatong Energy Co., Ltd. | Unit 1 (3.0 million tons/year): On August 6, 2026, the unit was throttled down to 70–80% capacity due to an operational issue; load was restored on August 14. From mid-October onwards, the unit is scheduled for a shutdown lasting approximately two weeks. Unit 2 (3.0 million tons/year): The unit was shut down on May 20, 2026, and restarted on June 3. On August 6, it was throttled down to 70–80% capacity due to an operational issue; load was restored on August 14. | ||
| Jiaxing Petrochemical Co., Ltd. | 1.5 million ton/year unit: Short shutdown for 5 days on March 13, 2026 due to operational issues; shut down on July 1 and restarted on September 3; shut down again around October 6. 2.2 million ton/year unit: Shut down on May 5, 2026, and currently in the process of restarting as of May 15, 2026. | ||
| Ningbo Yisheng Petrochemical Co., Ltd. | 2.0 million ton/year unit: Shutdown on January 25, 2025; 2.2 million ton/year unit: Shutdown on November 20, 2025, and restarted on December 24, 2025. | ||
| Sichuan Provincial Energy Investment Group Co., Ltd. | 1 million ton/year unit: Shutdown on April 15, 2026, postponed | ||
| Sinopec Yizheng Chemical Fibre Co., Ltd. | 650,000-ton unit: Shut down on April 10, 2024. 3,000,000-ton unit: Shut down on March 3, 2026, and restarted on March 20. Production was reduced to 70–80% of capacity from late July to early August before gradually recovering. | ||
| Xinjiang Zhongtai Chemical Co., Ltd. | 1.2 million tons/year unit: Shut down on July 1, 2026; restarted on July 25. Load increased to approximately 90% in early August; reduced to 80% in early September. Shutdown occurred on September 14 due to operational issues. Restarted on September 23; currently ramping up load while discharging product. | ||
| Yisheng Dahua Petrochemical Co., Ltd. | 2.25 Million Ton Per Annum (MTPA) Unit: Shut down on August 8, 2025; Restarted in July 15, 2026; Tripped due to an incident on August 26, 2026; Restarted on September 13, 2026. 3.75 MTPA Unit: Load reduced on October 31, 2025; Load increased on November 6, 2025; Technical revamp initiated on August 1, 2026. | ||
| Zhejiang Dushan Energy Co., Ltd. | **Unit 1 (2.5 Million Tons Capacity):** * **May 16, 2026:** Shutdown. * **June 15, 2026:** Restarted. * **August 4–14, 2026:** Reduced to 70% load due to operational issues. * **September 22, 2026:** Short shutdown due to technical issues, followed by repair and restoration of operations. * **November 2026:** Slight reduction in load. **Unit 2 (2.5 Million Tons Capacity):** * **February 10, 2026:** Shutdown. * **February 28, 2026:** Restarted. * **August 1, 2026:** Shutdown due to operational issues. * **August 23, 2026:** Restarted. * **November 2026:** Slight reduction in load. **Unit 1 (3.0 Million Tons Capacity):** * **June 12, 2026:** Load reduced. * **June 24, 2026:** Shutdown. * **July 24, 2026:** In the process of restarting. * **August 4–14, 2026:** Reduced to 70% load due to operational issues. * **November 2026:** Slight reduction in load. **Unit 2 (3.0 Million Tons Capacity):** * **April 14, 2026:** Shutdown. * **May 9, 2026:** Restarted. * **August 4–14, 2026:** Reduced to 70% load due to operational issues. * **October 3–28, 2026:** Shutdown. | ||
| Zhejiang Yisheng New Materials Co., Ltd. | Unit 1 (3.6 million tons/year capacity): - Temporarily shut down on February 24, 2026, due to unforeseen circumstances. - Restarted and ramping up load on February 25, 2026; fully restored to normal operation in early March 2026. - Began reducing load from March 12, 2026. - Reduced load by 30% on April 2, 2026. - Currently increasing load as of August 14, 2026. Unit 2 (3.6 million tons/year capacity): - Shut down on January 14, 2026. - Restarted and currently ramping up load as of February 25, 2026. - Reduced load by 30% on April 2, 2026. - Currently increasing load as of August 14, 2026. |
| Producer | Plant capacity (10kt) | Utilization % | Remark |
|---|---|---|---|
| BP Zhuhai Chemical Co., Ltd. | Shutdown scheduled for April 19, 2026; restart date to be determined. | ||
| Chongqing Pengwei Petrochemical Co., Ltd. | Shutdown on August 29, 2024 | ||
| Dongying Weilian Chemical Co., Ltd. | Load reduction and shutdown on June 29, 2026; restart and ramp-up in progress as of August 27. | ||
| Formosa Chemicals Industries (Ningbo) Co., Ltd. | Restart scheduled for May 9, 2026; currently undergoing shutdown as of June 30. | ||
| Fujian Billion Petrochemicals Co., Ltd. | Shutdown on November 1, 2026 | ||
| Fujian Fuhai Chuang Petrochemical Co., Ltd. | Shutdown on June 25, 2026; restart in early September. Power trip occurred on September 8 and was subsequently restored. In early November, product output and production volume were briefly affected. | ||
| Hainan Yisheng Petrochemical Co., Ltd. | Shutdown on August 16, 2025; Restart on June 1, 2026; Shutdown again on July 10. | ||
| Hanbang (Jiangyin) Petrochemical Co., Ltd. | Shutdown on January 6, 2025 | ||
| Hengli Petrochemical (Huizhou) Co., Ltd. | Shutdown scheduled for May 10, 2026, lasting approximately two weeks; followed by a short shutdown of 4–5 days starting on May 29. | ||
| Hengli Petrochemical Co., Ltd. | Shutdown on October 9, 2025; restart on October 24, 2025 | ||
| Jiangsu Hailun Petrochemical Co., Ltd. | Shutdown on August 28, 2025 | ||
| Jiangsu Honggang Petrochemical Co., Ltd. | Here is the professional translation of the operational schedule: **May 23, 2026:** Restarted; **June 1, 2026:** Resumed operations; **July 3, 2026:** Shut down; **September 1, 2026:** Restarted and ramping up production; **Late October – November 2026:** Reduced load (turndown), with early recovery anticipated. | ||
| Jiangsu Jiatong Energy Co., Ltd. | On August 6, 2026, the plant reduced its load to 70–80% due to operational issues; the load was restored on August 14. From mid-October onward, the plant underwent a shutdown for approximately two weeks. | ||
| Jiaxing Petrochemical Co., Ltd. | Short shutdown for 5 days starting March 13, 2026, due to unforeseen circumstances; unit shut down on July 1 and restarted on September 3; another shutdown occurred around October 6. | ||
| Ningbo Yisheng Petrochemical Co., Ltd. | Shutdown on January 25, 2025 | ||
| Sichuan Provincial Energy Investment Group Co., Ltd. | Shutdown on April 15, 2026, postponed | ||
| Sinopec Yizheng Chemical Fibre Co., Ltd. | Shutdown on April 10, 2024 | ||
| Xinjiang Zhongtai Chemical Co., Ltd. | The plant was shut down on July 1, 2026, and restarted on July 25. In early August, the load increased to approximately 90%. By early September, the load had decreased to around 80%. The unit experienced an unplanned shutdown on September 14 due to a technical issue. It was successfully restarted on September 23, with product discharge initiated and load ramping up in progress. | ||
| Yisheng Dahua Petrochemical Co., Ltd. | Shutdown on August 8, 2025; Restarting on July 15, 2026; Shutdown due to operational issues on August 26; Restarted on September 13. | ||
| Zhejiang Dushan Energy Co., Ltd. | Shutdown on May 16, 2026; Restart on June 15, 2026. Reduced to 70% capacity from August 4–14 due to operational issues. Brief shutdown for repairs on September 22 following an incident. Slight load reduction in November. | ||
| Zhejiang Yisheng New Materials Co., Ltd. | On February 24, 2026, the unit was temporarily shut down due to unforeseen circumstances. Load was restored on February 25, with full operational capacity resumed in early March. From March 12 onward, the load was reduced. On April 2, a 30% load reduction was implemented. As of August 14, the load is being gradually increased. |
| Producer | Plant capacity (10kt) | Utilization % | Remark |
|---|---|---|---|
| BP Zhuhai Chemical Co., Ltd. | Shutdown on April 19, 2026; restart date TBD. | ||
| Chongqing Pengwei Petrochemical Co., Ltd. | Shutdown on August 29, 2024 | ||
| Dongying Weilian Chemical Co., Ltd. | Unit load reduction and shutdown on June 29, 2026; restart with gradual load ramp-up underway as of August 27. | ||
| Formosa Chemicals Industries (Ningbo) Co., Ltd. | Restart on May 9, 2026; Shutdown in progress as of June 30. | ||
| Fujian Billion Petrochemicals Co., Ltd. | Shutdown on November 1, 2026. | ||
| Fujian Fuhai Chuang Petrochemical Co., Ltd. | Shutdown scheduled for June 25, 2026, with restart in early September; power trip occurred on September 8, followed by restoration; brief impact on product quality and output in early November. | ||
| Hainan Yisheng Petrochemical Co., Ltd. | Shutdown on August 16, 2025; Restart on June 1, 2026; Shutdown on July 10. | ||
| Hanbang (Jiangyin) Petrochemical Co., Ltd. | Shutdown on January 6, 2025; | ||
| Hengli Petrochemical (Huizhou) Co., Ltd. | Shutdown scheduled for May 10, 2026, lasting approximately two weeks; followed by a short-term shutdown of 4–5 days starting on May 29. | ||
| Hengli Petrochemical Co., Ltd. | Shutdown on October 9, 2025; restart on October 24, 2025. | ||
| Jiangsu Hailun Petrochemical Co., Ltd. | Shutdown on August 28, 2025; | ||
| Jiangsu Honggang Petrochemical Co., Ltd. | May 23, 2026: Restart scheduled for June 1; July 3: Shutdown; September 1: Restart and ramp-up in progress; Late October to November: Load reduction, with early restoration planned. | ||
| Jiangsu Jiatong Energy Co., Ltd. | On August 6, 2026, the plant load was reduced to 70–80% due to operational issues. The load was restored on August 14. From mid-October onwards, the unit was shut down for approximately two weeks. | ||
| Jiaxing Petrochemical Co., Ltd. | A 5-day unplanned shutdown occurred on March 13, 2026; the unit was shut down on July 1 and restarted on September 3; another shutdown took place around October 6. | ||
| Ningbo Yisheng Petrochemical Co., Ltd. | Shutdown on January 25, 2025 | ||
| Sichuan Provincial Energy Investment Group Co., Ltd. | The shutdown scheduled for April 15, 2026, has been postponed. | ||
| Sinopec Yizheng Chemical Fibre Co., Ltd. | Shutdown on April 10, 2024; | ||
| Xinjiang Zhongtai Chemical Co., Ltd. | Shutdown on July 1, 2026; restart on July 25. Load increased to approximately 90% in early August; decreased to 80% in early September. Unplanned shutdown occurred on September 14 due to operational issues; restarted on September 23 with product discharge and load ramp-up currently underway. | ||
| Yisheng Dahua Petrochemical Co., Ltd. | Shutdown on August 8, 2025; Restart in progress as of July 15, 2026; Shutdown due to unforeseen circumstances on August 26, with restart completed on September 13. | ||
| Zhejiang Dushan Energy Co., Ltd. | Shutdown on May 16, 2026; restart on June 15. Reduced load to 70% due to operational issues from August 4 to 14. Short shutdown for repairs due to unforeseen circumstances on September 22. Minor load reduction in November. | ||
| Zhejiang Yisheng New Materials Co., Ltd. | The unit was temporarily shut down on February 24, 2026, due to unforeseen circumstances. It resumed load ramp-up on February 25 and returned to full operation in early March. Starting March 12, the load was reduced; on April 2, a 30% load reduction was implemented. As of August 14, the unit is undergoing load increase. |